Meanwhile, as Ye Ying led his men to extensively recruit people for the Han Tribe in the Youqiao Clan, various Engineering Construction in the south were also progressing rapidly.
With the railway Road Building Team split into two, each receiving a thousand demobilized soldiers, along with a large number of engineering vehicles and machinery, the efficiency of railway laying increased by more than double compared to before.
In addition, with the continuous influx of resources from the northern industries, large quantities of equipment and building materials were transported to the south, greatly supporting the construction in the south and causing the mileage of several railway lines currently under construction in the south to soar.
In just two months, the Qi-Tai Line Railway, which runs along the Liuyang River and the Cheng-Qi Line Railway, was completed. The first section is 227 kilometers long.
The railway from Qian Commandery to Taigang Commandery was originally divided into four sections by the Engineering Team. The longest and easiest section to build was the first section, because it was a flat plain. There was no need to build bridges or dig tunnels. All that was needed was to use excavators to level the ground, loaders to raise the foundation, and Road Roller to roll it over several times before sleepers could be laid and rails nailed on top. This section of the road was very easy to build.
Although the second section was the most difficult part of the entire Qi-Tai Line Railway project, the continuous support from the rear allowed the project to proceed quickly.
Because more Rock Drill were sent from the rear, the Engineering Team was able to excavate the tunnel day and night. In any case, even during the day, they were inside the tunnel and it looked almost the same as at night.
A large quantity of explosives and fuses were also delivered from the rear, in tens of tons at a time. With this inexhaustible supply of high-quality explosives, the tunnel excavation became much easier than before.
Now, with the combined support of Rock Drill and explosives, the entire Engineering Team can drill a distance of more than ten meters every day. First, the Rock Drill is used to cut the groove, then holes are drilled and blasted, and finally loaders and tractors come in to transport all the rubble away, and then the previous operation is repeated.
As for the uneven, pitted tunnel walls, that was done by another group of people later on.
They got an excavator and replaced the bucket with a basket. A person sits in the basket and can use a handheld Pneumatic Pick to drill holes in the tunnel wall. The holes are for driving expansion bolts in. Although the Han Tribe does not yet have dedicated expansion bolts, they can use wood and steel bars as substitutes.
After nailing nails into the stone walls of the entire tunnel, the pre-stitched steel cage can be tied to it with wire, and then wooden support templates can be installed from below before filling it with concrete.
Once this layer of Reinforced Concrete dries, no matter how pitted and uneven the original stone wall was, it will eventually become very smooth.
The process of pouring concrete was particularly arduous. Previously, the Han Tribe had water pumps, air pumps, and oil pumps, but no pump that could suck up and spray concrete.
To solve the problem of difficult tunnel wall pouring, Luo Chong specially commissioned the development of a new type of concrete pump. Unlike the various Plunger Pump and air pumps of the past, this concrete pump has a larger cavity to accommodate the rough concrete consisting entirely of gravel, sand, and cement.
In addition, its pumping principle is different from that of the original water pump, air pump, and oil pump. The pumping principle of the concrete pump is like the rubber ball that pressurizes a blood pressure gauge. First, a huge window is opened in the pumping chamber, and then a rubber bubble made of composite material is sealed and installed at the window.
The rubber Steam Drum is connected to the piston of the Steam Engine. By using the principle of pushing and pulling (squeezing) the rubber steam Steam Drum with the Steam Engine, the pump chamber is pressurized and depressurized. This is how concrete is absorbed and sprayed.
Of course, in order to improve the durability of the concrete pump, that is, its service life, Luo Chong also specially asked the Comprehensive Research Institute to make a composite material rubber Steam Drum.
This rubber Steam Drum has a multi-layered structure. Both sides are made of black rubber, but inside it is like a sandwich, with several layers of Sisal Fiber cloth and wire Iron Fabric sandwiched inside.
Such a complex process makes this rubber Steam Drum difficult to deform, and it is very difficult to use manually. However, this thing was originally designed to be used with Steam Engine. In addition, the cost is relatively high, but the high price brings an extended service life.
A rubber part that originally could only be used for one month now costs five times more but can be used for two years. How do you calculate that? It's definitely a huge improvement in cost-effectiveness!
With the assistance of these high-tech tools, the tunnel excavation speed is astonishing. The Number One Tunnel is a little over three kilometers long. The Engineering Team has now split into two groups, digging from both ends toward the middle at the same time. Meanwhile, three other teams are digging Vertical Shaft in the middle and expanding outwards. Although the teams in the middle cannot use Rock Drill, they have small pneumatic Pneumatic Pick and explosives available, so their progress is not slow either.
In addition to these tunnels, the second section of the route also includes several Canyon Bridge. These Canyon Bridge are flanked by cliffs with deep abysses in between. The Engineering Team ultimately had to choose this type of terrain in order to save on railway mileage.
However, since it was a carefully chosen location, it must be a place that is convenient for building a bridge.
One of the "extra-large" canyon railway bridges, with a span of over 120 meters, caused considerable trouble for the Engineering Team.
With cliffs on both sides and a deep canyon tens of meters deep in the middle, building a bridge and transporting materials were both problems.
Finally, an engineer from the Xingang Commandery Power Research Institute came up with an idea. This man had often traveled from Xingang Commandery to Hanyang City via Horse Binding Pass, so he had some knowledge of the place.
There is a Walled Enclosure in the valley outside Horse Binding Pass. The walls of the Walled Enclosure are equipped with more than a dozen ballistae. The ballistae have a range of several hundred meters, and the bolts are heavy enough that they can fly a long distance even when tied with a rope.
So his idea was to get a ballista, attach thin hemp ropes to the javelins, and use the ballista to shoot them at the other side.
First, use a ballista to carry the thin hemp rope across, then use the thin hemp rope to tie a thicker rope across, and finally replace the rope with Steel Cable. Once the Steel Cable are erected on both sides, equipment, personnel, and building materials can be hoisted across the middle of the canyon using the Steel Cable.
Everyone thought it was a good idea, but when the matter was reported to You Fu, it was immediately rejected by You Fu.
You Fu then came to the edge of the cliff and said to the group, "Your idea is good, but is a distance of 120 meters really worth using a ballista? You can just use any longbow to shoot the rope across. If we were to transport a ballista for you, it would take half a month from sending the message to getting the ballista here."
He reprimanded the men and then ordered someone to bring over a longbow. With a longbow and heavy arrows, the arrows could be Lobbed Shot at least 300 meters. Even with a thin hemp rope attached, which would increase the resistance, the arrows would still be enough to cross the 120-meter-wide chasm.
You Fu drew his bow, nocked an arrow, and aimed at the sky opposite the cliff. With a whoosh, the arrow arced high into the air and landed precisely on the grass on the opposite cliff.
"See that? It's such a short distance, why bother bringing a ballista over?!"
The engineers were all so embarrassed that they couldn't speak.
These people were selected directly from the university to work in the research institute. They were proficient in calculation and mechanics, but sometimes they liked to get stuck on details and make simple things complicated.
It's like trying to prove '1+1=2' using advanced calculus.
P. S.: Narrow-Gauge Railway are the kind that can be laid and used immediately, so they are relatively simple to build. Please don't criticize the construction progress.